[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138475":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138475,798,2,"多选题","措施费包括（ ）所需要的各项费用。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","环境保护费",true,{"key":16,"text":17,"correct":14},"B","大型机械设备进出场及安拆费",{"key":19,"text":20,"correct":14},"C","混凝土、钢筋混凝土模板及支架费",{"key":22,"text":23,"correct":24},"D","工程排污费",false,{"key":26,"text":27,"correct":14},"E","已完工程及设备保护费","ABCE","2005年建设工程经济真题第75题 本题考查的是措施费的内容。 措施费主要包括环境保护费、文明施工费、安全施工费、临时设施费、夜间施工增加费、二次搬运费、大型机械设备进出场及安拆费、混凝土、钢筋混凝土模板及支架费、脚手架费、已完工程及设备保护费、施工排水降水费。工程排污费属于规费的范畴。 综上所述，本题正确答案为ABCE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]