[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138450":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138450,798,2,"多选题","建设投资可以分为静态投资和动态投资部分，下列属于动态投资的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设期利息",true,{"key":16,"text":17,"correct":14},"B","涨价预备费",{"key":19,"text":20,"correct":21},"C","建筑安装工程费",false,{"key":23,"text":24,"correct":21},"D","基本预备费",{"key":26,"text":27,"correct":21},"E","工程建设其他费","AB","本题主要考查了建设工程项目总投资的概念。 建设投资可分为静态投资部分和动态投资部分。 静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。 动态投资部分包括涨价预备费、建设期利息等。 综上所述，本题正确答案为AB项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]