[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138443,798,1,"单选题","下列建设工程项目相关费用中，属于工程建设其他费用的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","环境影响评价费",true,{"key":16,"text":17,"correct":18},"B","建筑安装工程费",false,{"key":20,"text":21,"correct":18},"C","设备及工器具购置费",{"key":23,"text":24,"correct":18},"D","预备费","2011年建设工程经济真题第60题 本题主要考查了建设工程项目总投资的组成。 建设工程项目总投资组成见下表： A项：如表所示，环境影响评价费属于工程建设其他费用。因此，A 项正确。 BC项：建筑安装工程费和设备及工器具购置费属于工程费用。因此，BC项不当选。 D项：预备费和工程建设其他费用是平级，不存在从属关系。因此，D项不当选。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]