[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138435,798,1,"单选题","(2014真题)关于设计概算的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计概算是确定和控制建设工程项目全部投资的文件",false,{"key":16,"text":17,"correct":18},"B","编制设计概算不需考虑建设项目施工条件对投资的影响",true,{"key":20,"text":21,"correct":14},"C","如果设计概算值超过投资控制额，必须修改设计或重新立项审批",{"key":23,"text":24,"correct":14},"D","设计概算由项目设计单位负责编制，并对其编制质量负责","建设工程项目设计概算是设计文件的重要组成部分，是确定和控制建设工程项目全部投资的文件。设计概算投资一般应控制在立项批准的投资控制额以内；如果设计概算值超过控制额，必须修改设计或重新立项审批。设计概算应考虑建设项目施工条件等因素对投资的影响；还应按项目合理工期预测建设期价格水平，以及资产租赁和贷款的时间价值等动态因素对投资的影响。设计概算由项目设计单位负责编制，并对其编制质量负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]