[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138426,798,1,"单选题","某砖混结构墙体砌筑工程完成10m3砖墙需基本用工为26个工日，辅助用工为5个工日，超距离运砖需2个工日，人工幅度差系数为10%，则预算定额人工工日消耗量为（ ）工日／10m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","36.3",true,{"key":16,"text":17,"correct":18},"B","35.8",false,{"key":20,"text":21,"correct":18},"C","35.6",{"key":23,"text":24,"correct":18},"D","33.7","本题主要考查了人工消耗指标的计算。 计算人工消耗量是按照综合取定的工程量或单位工程量和劳动定额中的时间定额，计算出各种用工的工作日数量，即 预算定额人工工日消耗量=基本用工工日+超运距用工工日+辅助用工工日+人工幅度差用工工日 其中，人工幅度差用工工日=（基本用工工日+超运距用工工日+辅助用工工日）×人工幅度差系数 本题中，人工幅度差用工工日=（26+2+5）×10%=3.3（工日） 预算定额人工工日消耗量=26+2+5+3.3=36.3（工日） 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]