[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138422":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138422,798,1,"单选题","下列机械工作时间消耗中，属于机械台班使用定额中不可避免的无负荷工作时间的是（ ）。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","汽车在运送土方时没有装满导致的延长时间",false,{"key":16,"text":17,"correct":18},"B","筑路机在工作区末端调头的时间",true,{"key":20,"text":21,"correct":14},"C","未及时供给机械燃料而导致的停工时间",{"key":23,"text":24,"correct":14},"D","暴雨时压路机被迫停工时间","本题考查的是机械台班使用定额的编制。不可避免的无负荷工作时间，是指由施工过程的特点和机械结构的特点造成的机械无负荷工作时间。例如筑路机在工作区末端调头等，都属于此项工作时间的消耗。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]