[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138418":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138418,798,2,"多选题","(2014真题)编制预算定额人工消费指标时，下列人工消耗量属于人工幅度差用工的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工过程中水电维修用工",true,{"key":16,"text":17,"correct":14},"B","隐蔽工程验收影响的操作时间",{"key":19,"text":20,"correct":21},"C","现场材料水平搬运用工",false,{"key":23,"text":24,"correct":21},"D","现场材料加工用工",{"key":26,"text":27,"correct":21},"E","现场筛砂子增加的用工量","AB","人工幅度差用工，指人工定额中未包括的，而在一般正常施工情况下又不可避免的一些零星用工，其内容如下：(1)各种专业工种之间的工序搭接及土建工程与安装工程的交叉、配合中不可避免的停歇时间；(2)施工机械在场内单位工程之间变换位置及在施工过程中移动临时水电线路引起的临时停水、停电所发生的不可避免的间歇时间；(3)施工过程中水电维修用工；(4)隐蔽工程验收等工程质量检查影响的操作时间；(5)现场内单位工程之间操作地点转移影响的操作时间；(6)施工过程中工种之间交叉作业造成的不可避免的剔凿、修复、清理等用工；(7)施工过程中不可避免的直接少量零星用工。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]