[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138417":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138417,798,2,"多选题","机械工作时间的消耗，按其性质可分为必须消耗的时间和损失时间，其中必须消耗的时间包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","停工时间",false,{"key":16,"text":17,"correct":18},"B","有效工作时间",true,{"key":20,"text":21,"correct":14},"C","低负荷下的工作时间",{"key":23,"text":24,"correct":18},"D","不可避免的无负荷工作时间",{"key":26,"text":27,"correct":18},"E","不可避免的中断时间","BDE","本题考查的是施工机械台班使用定额的编制。 机械工作时间的消耗，按性质可分为必须消耗的时间和损失时间两大类。其中必须消耗的工作时间包括有效工作、不可避免的无负荷工作和不可避免的中断三项时间消耗。 综上所述，本题的正确答案为BDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]