[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138414":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138414,798,2,"多选题","编制施工机械台班使用定额时，属于机械工作实践中损失时间的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工本身原因造成的停工时间",true,{"key":16,"text":17,"correct":14},"B","非施工原因造成的停工时间",{"key":19,"text":20,"correct":14},"C","违反劳动纪律引起的时间损失",{"key":22,"text":23,"correct":24},"D","工人正常的休息时间",false,{"key":26,"text":27,"correct":14},"E","低负荷下的工作时间","ABCE","2012年建设工程经济真题第66题 本题主要考查了施工机械台班使用定额的编制。 机械工作时间分为必需消耗的时间和损失时间两类。 ABCE项：如图所示，选项ABCE均属于损失时间。 D项：工人正常休息的时间是属于必需消耗的时间，故D项错误。 综上所述，本题正确答案为ABCE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]