[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138412,798,1,"单选题","施工机械工作时间不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有效工作时间",false,{"key":16,"text":17,"correct":18},"B","可避免的无负荷工作时间",true,{"key":20,"text":21,"correct":14},"C","不可避免的中断时间",{"key":23,"text":24,"correct":14},"D","正常负荷下的工作时间","本题主要考查了施工机械时间定额的编制。 施工机械时间定额的分类如图： 如表所示，有效工作时间、不可避免的中断时间和正常负荷下的工作时间均属于机械工作时间。 本题为选非题，综上所述，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]