[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138410,798,1,"单选题","某机械台班产量为4m3，与之配合的工人小组由5人组成，则单位产品的人工时间定额为（ ）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.50",false,{"key":16,"text":17,"correct":14},"B","0.80",{"key":19,"text":20,"correct":14},"C","1.20",{"key":22,"text":23,"correct":24},"D","1.25",true,"2013年建设工程经济真题第31题 本题考查的是单位产品人工时间定额的计算。 单位产品人工时间定额（工日）=小组成员总人数\u002F台班产量=5\u002F4=1.25工日。 综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]