[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138406":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138406,798,1,"单选题","(2014真题)在机械工作时间消耗分类中，由于人工装料数量不足引起的机械不能满负荷工作的时间属于()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","有根据地降低负荷下的工作时间",false,{"key":16,"text":17,"correct":14},"B","机械的多余工作时间",{"key":19,"text":20,"correct":14},"C","正常负荷下的有效工作时间",{"key":22,"text":23,"correct":24},"D","低负荷下的工作时间",true,"低负荷下的工作时间，是由于工人或技术人员的过错所造成的施工机械在降低负荷的情况下工作的时间。例如，工人装车的砂石数量不足引起的汽车在降低负荷的情况下工作所延续的时间。此项工作时间不能作为计算时间定额的基础。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]