[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138392":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138392,798,1,"单选题","在合理的劳动组织和正常的施工条件下，完成某单位合格分项工程的时间消耗为所有班组完成时间均不超过1个工日，其中个别班组可以在0.50工日完成，多数班组经过努力可以在0.80工日完成。则编制施工定额时，人工消耗宜为（）工日。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.00",false,{"key":16,"text":17,"correct":18},"B","0.80",true,{"key":20,"text":21,"correct":14},"C","0.77",{"key":23,"text":24,"correct":14},"D","0.50","本题考查的是施工定额的编制。施工定额水平必须遵循平均先进的原则。所谓平均先进水平，是指在正常的生产条件下，多数施工班组或生产者经过努力可以达到，少数班组或劳动者可以接近，个别班组或劳动者可以超过的水平。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]