[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138390,798,1,"单选题","(2014真题)完成某预算定额项目单位工程量的基本用工为2.8工日，辅助用工为0.7工日，超运距用工为0.9工日，人工幅度差系数为10%，该定额的人工工日消耗量为()工日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4.84",true,{"key":16,"text":17,"correct":18},"B","4.75",false,{"key":20,"text":21,"correct":18},"C","4.56",{"key":23,"text":24,"correct":18},"D","4.68","人工幅度差用工数量=∑（基本用工+超运距用工+辅助用工）*人工幅度差系数=(2.8+0.9+0.7)*10%=0.44（工日），人工消耗量指标=基本用工+超运距用工+辅助用工+人工幅度差用工=2.8+0.9+0.7+0.44=4.84（工日）。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]