[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138377,798,1,"单选题","编制人工定额时，基本工作结束后的整理劳动工具时间应计入（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","休息时间",false,{"key":16,"text":17,"correct":14},"B","不可避免的中断时间",{"key":19,"text":20,"correct":21},"C","有效工作时间",true,{"key":23,"text":24,"correct":14},"D","损失时间","本题考查的是人工定额的编制。在工人工作时间分类中，定额（消耗）时间包括有效工作时间、休息时间、不可避免的中断时间；其中，整理工具用具所需要的时间，属于有效工作时间中的准备与结束时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]