[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138374":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138374,798,2,"多选题","人工定额中的定额时间不包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工人下班前对搅拌机进行清洗的时间",false,{"key":16,"text":17,"correct":14},"B","工人由于施工工艺原因必需的中断时间",{"key":19,"text":20,"correct":21},"C","由于设计错误造成的工人窝工时间",true,{"key":23,"text":24,"correct":14},"D","工人必须的休息时间",{"key":26,"text":27,"correct":21},"E","由于施工机械故障造成的工人窝工时间","CE","2006年建设工程经济真题第80题 本题考查的是人工定额的形式。 定额时间是指工人在正常施工条件下，为完成工作任务所消耗的时间。定额时间包括有效工作时间、休息时间和不可避免的中断时间。有效工作时间还包括基本工作时间、辅助工作时间和准备与结束工作时间，故ABD都属于定额时间。 本题为选非题，综上所述，本题应选择C、E。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]