[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138371":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138371,798,2,"多选题","在制订人工定额时，拟定施工作业定额时间是在拟定（ ）的基础上编制的。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间",true,{"key":16,"text":17,"correct":14},"B","辅助工作时问",{"key":19,"text":20,"correct":21},"C","超负荷下的工作时间",false,{"key":23,"text":24,"correct":14},"D","休息时间",{"key":26,"text":27,"correct":14},"E","不可避免的中断时间","ABDE","本题主要考查了人工定额的编制。 施工作业的定额时间是在拟定基本工作时间、辅助工作时间、准备与结束工作时间、不可避免的中断时间以及休息时间的基础上编制的。 综上所述，本题正确答案为ABDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]