[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138363,798,1,"单选题","编制人工定额时，工人在工作班内消耗的工作时间属于损失时间的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","停工时间",true,{"key":16,"text":17,"correct":18},"B","休息时间",false,{"key":20,"text":21,"correct":18},"C","准备与结束工作时间",{"key":23,"text":24,"correct":18},"D","不可避免中断时间","2007年建设工程经济真题第31题 本题主要考查了人工定额的编制。 工人工作时间的分类如图： A项：如图所示，停工时间属于损失时间，故当选。 BCD项：休息时间、准备与结束工作时间和不可避免中断时间均属于必须消耗的时间。因此，BCD项错误。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]