[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138362,798,1,"单选题","某斗容量1m3正铲挖土机的机械台班产量为4.96（定额单位100m3），小组成员两人，则挖100m3土的人工时间定额为（ ）工日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.40",true,{"key":16,"text":17,"correct":18},"B","0.20",false,{"key":20,"text":21,"correct":18},"C","2.48",{"key":23,"text":24,"correct":18},"D","4.96","2010年建设工程经济真题第46题 本题主要考查了人工定额的形式。 人工定额按表现形式的不同，可分为时间定额和产量定额，二者互为倒数。 时间定额以工日为单位，每一工日按八小时计算。 因此，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]