[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138361":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138361,798,1,"单选题","根据计时观察法测得某工序工人工作时间：基本工作时间48min，辅助工作时间5min，准备与结束工作时间4min，休息时间3min，不可避免的中断时间2min，停工时间1min，则定额时间是（ ）min。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","56",false,{"key":16,"text":17,"correct":14},"B","60",{"key":19,"text":20,"correct":21},"C","62",true,{"key":23,"text":24,"correct":14},"D","63","本题考查的是人工定额时间的内容。 施工作业的定额时间，是在拟定基本工作时间、辅助工作时间、准备与结束时间、不可避免的中断时间以及休息时间的基础上编制的。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]