[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138360,798,1,"单选题","已知某工人班组完成某单位产品所必须的工作时间为2.5个小时，则该产品的产量定额为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.4",true,{"key":16,"text":17,"correct":18},"B","4",false,{"key":20,"text":21,"correct":18},"C","3.2",{"key":23,"text":24,"correct":18},"D","0.3125","本题主要考查了人工定额的形式。 人工定额按表现形式的不同，可分为时间定额和产量定额两种形式。 时间定额就是某种专业，某种技术等级工人班组或个人，在合理的劳动组织和合理使用材料的条件下，完成单位合格产品所必需的工作时间； 时间定额与产量定额互为倒数，即： 本题中，某工人班组完成某单位产品所必须的工作时间为2.5个小时，即时间定额为2.5个小时，则 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]