[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138347":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138347,798,2,"多选题","按照反映的生产要素消耗内容，可将建设工程定额分为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建筑工程定额",false,{"key":16,"text":17,"correct":14},"B","安装工程定额",{"key":19,"text":20,"correct":21},"C","人工定额",true,{"key":23,"text":24,"correct":21},"D","材料消耗定额",{"key":26,"text":27,"correct":21},"E","机械台班定额","CDE","2004年建设工程经济真题第80题 本题考查的是建设工程定额的分类。 建设工程按生产要素内容分类，可以分为人工定额、材料消耗定额和施工机械台班使用定额。 综上所述，本题的正确答案为CDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]