[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138343,798,1,"单选题","材料消耗定额是在合理和节约使用材料的条件下，生产单位质量（ ）产品所必须消耗的一定规格的材料、成品、半成品和水、电等资源的数量标准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","低劣",false,{"key":16,"text":17,"correct":18},"B","合格",true,{"key":20,"text":21,"correct":14},"C","高档",{"key":23,"text":24,"correct":14},"D","低档","2005年建设工程经济真题第58题 本题考查的是材料消耗定额的概念。 建设工程定额按生产要素内容分为人工定额、材料消耗定额和施工机械台班使用定额。材料消耗定额是指在合理和节约使用材料的条件下，生产单位合格产品所必须消耗的一定规格的材料、成品、半成品和水、电等资源的数量标准。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]