[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138336,798,1,"单选题","以工序为编制对象的定额（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工定额",true,{"key":16,"text":17,"correct":18},"B","基础定额",false,{"key":20,"text":21,"correct":18},"C","概算定额",{"key":23,"text":24,"correct":18},"D","概算指标","2007年建设工程经济真题第55题 本题主要考查了建设工程定额按编制程序和用途分类。 施工定额是以同一性质的施工过程---工序作为研究对象，表示生产产品数量与时间消耗综合关系的定额。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]