[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138108":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138108,798,2,"多选题","根据《企业会计准则第15号——建造合同》，按累计实际发生的合同成本占合同预计总成本的比例确定合同完工进度时，累计实际发生的合同成本不包括（ ）。( 2015真题 )",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","已订立采购合同但尚未运抵现场的材料成本",true,{"key":16,"text":17,"correct":14},"B","已采购进场但施工中尚未安装的材料成本",{"key":19,"text":20,"correct":14},"C","在分包工程的工作量完成之前预付给分包单位的款项",{"key":22,"text":23,"correct":24},"D","已经完成并验收合格的设备安装工程的价款",false,{"key":26,"text":27,"correct":24},"E","已经完成并验收合格的分包工程的合同价款","ABC","本题考查的是建造（施工）合同收入的确认。累计实际发生的合同成本不包括施工中尚未安装或使用的材料成本等与合同未来活动相关的合同成本，也不包括在分工工程的工程量完成之前预付给分包单位的款项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]