[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138103":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138103,798,2,"多选题","(2014真题)确定建造（施工）合同完工进度的方法有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","根据实际合同收入与预计收入的比例确定",false,{"key":16,"text":17,"correct":18},"B","根据累计实际发生的合同成本占合同预计总成本的比例确定",true,{"key":20,"text":21,"correct":18},"C","根据已经完成的合同工作量占合同预计总工作量的比例确定",{"key":23,"text":24,"correct":18},"D","根据已经完成合同工作的技术测量确定",{"key":26,"text":27,"correct":14},"E","根据合同初始价格与工程预算价格的比例确定","BCD","确定建造（施工）合同完工进度有以下三种方法：(1)根据累计实际发生的合同成本占合同预计总成本的比例确定；(2)根据已经完成的合同工作量占合同预计总工作量的比例确定；(3)根据已完成合同工作的技术测量确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]