[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138097":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138097,798,2,"多选题","当建筑企业不能可靠地估计施工合同的结果时，对当期合同收入和费用的确认方法是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同成本能够收回的，只据实确认合同收入，不确认费用",false,{"key":16,"text":17,"correct":18},"B","合同成本能够收回的，据实确认合同收入，同时确认费用",true,{"key":20,"text":21,"correct":18},"C","合同成本不能够收回的，只据实确认费用，不确认合同收入",{"key":23,"text":24,"correct":14},"D","合同成本不能够收回的，据实确认合同收入，同时确认费用",{"key":26,"text":27,"correct":14},"E","合同成本不能够收回的，据实确认合同收入，不确认费用","BC","本题主要考查了建造（施工）合同收入的确认。 当建筑业企业不能可靠地估计建造（施工）合同的结果时，就不能采用完工百分比法来确认和计量当期的合同收入，应区别以下两种情况进行处理： （1）合同成本能够回收的，合同收入根据能够收回的实际合同成本来确认，合同成本在其发生的当期确认为费用； （2）合同成本不能回收的，应在发生时立即确认为费用，不确认为合同收人。 综上所述，本题正确答案为BC项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]