[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138093":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138093,798,1,"单选题","对于合同结果不能可靠地估计，合同成本能够确认的施工合同，其合同收入应按照（ ）确认。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同初始收入",false,{"key":16,"text":17,"correct":14},"B","实际合同成本+合理利润",{"key":19,"text":20,"correct":14},"C","已经发生的全部成本",{"key":22,"text":23,"correct":24},"D","得到确认的实际合同成本",true,"2010年建设工程经济真题第51题 本题主要考查了建造（施工）合同收入的确认。 合同结果不能够可靠估计时，应区别以下两种情况进行处理： （1）合同成本能够回收的，合同收入根据能够收回的实际合同成本来确认，合同成本在其发生的当期确认为费用； （2）合同成本不能够回收的，应在发生时立即确认为费用，不确认收入。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]