[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138075,798,1,"单选题","下列各项中，不能用于确定合同完工进度的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预先计划的完工进度",true,{"key":16,"text":17,"correct":18},"B","已经完成的合同工作量占合同预计总工作量的比例",false,{"key":20,"text":21,"correct":18},"C","技术测量的完工进度",{"key":23,"text":24,"correct":18},"D","累计实际发生的合同成本占合同预计总成本的比例","本题主要考查了建造（施工）合同完工进度的确定。 确定建造（施工）合同完工进度有以下三种方法： （1）根据累计实际发生的合同成本占合同预计总成本的比例确定； （2）根据已经完成的合同工作量占合同预计总工作量的比例确定； （3）根据已完成合同工作的技术测量确定。 本题为选非题，综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]