[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138010,798,1,"单选题","在工程成本核算中，要做到（ ）三同步。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","形象进度、产值统计、实际成本归集",true,{"key":16,"text":17,"correct":18},"B","形象进度、合同履约、产值归集",false,{"key":20,"text":21,"correct":18},"C","计划成本、责任成本、实际成本归集",{"key":23,"text":24,"correct":18},"D","产值统计、责任成本、实际成本归集","本题主要考查了工程成本核算的基本任务和基本要求。 加强成本核算的基础工作，要求建立、健全与成本核算有关的各项原始记录和工程量统计制度，做到形象进度、产值统计、实际成本归集三同步，即三者的取值范围应是一致的。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]