[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1137884,798,1,"单选题","某工程有甲、乙、丙、丁四个实施方案可供选择。四个方案的投资额依次是60万元、80万元、100万元和120万元。年运行成本依次是16万元、13万元、10万元和6万元，各方案应用环境相同。设基准投资率为10%。则采用折算费用法选择的最优方案为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","甲",false,{"key":16,"text":17,"correct":14},"B","乙",{"key":19,"text":20,"correct":14},"C","丙",{"key":22,"text":23,"correct":24},"D","丁",true,"2011年建设工程经济真题第8题 本题中的各方案折算费用计算为： 甲的折算费用= 16+60×10% = 22万元 乙的折算费用= 13+80×10% =21万元 丙的折算费用= 10+100×10% =20万元 丁的折算费用= 6+120×10% =18万元 在多方案比较时，选择折算费用最小的方案。本题中丁的折算费用最小，所以应选择丁方案。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]