[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137857":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137857,798,2,"多选题","价值工程对象选择的方法有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","ABC分析法",true,{"key":16,"text":17,"correct":14},"B","强制确定法",{"key":19,"text":20,"correct":14},"C","百分比分析法",{"key":22,"text":23,"correct":14},"D","因素分析法",{"key":25,"text":26,"correct":27},"E","年数总和法",false,"ABCD","本题主要考查了价值工程准备阶段。 ABCD项：价值工程对象选择的方法有很多种，不同方法适宜于不同的价值工程对象，根据企业条件选用适宜的方法，就可以取得较好效果。常用的方法有因素分析法、ABC分析法、强制确定法、百分比分析法、价值指数法等。因此，ABCD项正确。 E项：年数总和法是固定资产计提折旧的方法。因此，E项错误。 综上所述，本题正确答案为ABCD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]