[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137853":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137853,798,2,"多选题","在价值工程活动中，计算功能评价值前应完成的工作有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","功能现实成本计算",true,{"key":16,"text":17,"correct":18},"B","方案创造",false,{"key":20,"text":21,"correct":18},"C","方案评价",{"key":23,"text":24,"correct":14},"D","功能整理",{"key":26,"text":27,"correct":14},"E","功能定义","ADE","2009年建设工程经济真题第65题 本题主要考查了价值工程的工作程序。 价值工程的工作程序步骤图如下： 如图所示，功能评价之前应完成工作对象的选择、信息资料的搜集、功能定义、功能整理和功能成本分析。 综上所述，本题正确答案为ADE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]