[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1137824,798,1,"单选题","价值工程活动中，计算产品成品的方法是以产品（ ）为中心分析成本的事前成本计算方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","功能",true,{"key":16,"text":17,"correct":18},"B","质量",false,{"key":20,"text":21,"correct":18},"C","价格",{"key":23,"text":24,"correct":18},"D","性能","2012年建设工程经济真题第47题 本题主要考查了价值工程的概念。 价值工程废弃了会计制度上沿用的事后成本和与产品费用无关的计算成本办法，采用以产品功能为中心分析成本的事前成本计算方法，保证了成本的正确可靠性。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]