[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1137755,798,1,"单选题","某设备5年前的原始成本是10万元，现账面价值是3万元，市场价值是2万元，则该设备的沉没成本为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","7",{"key":23,"text":24,"correct":18},"D","8","2013年建设工程经济真题第4题 本题考查的是沉没成本的计算。 沉没成本是既有企业过去投资决策发生的、非现在决策能改变（或不受现在决策影响）、已经计入过去投资费用回收计划的费用。在进行设备更新分析时，旧设备往往会产生一笔沉没成本，即：沉没成本=设备账面价值-当前市场价值=3-2=1（万元）。 综上所述，本题的正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]