[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137698":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137698,798,2,"多选题","资本金现金流量表中，作为现金流出的项目有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","借款本金偿还",true,{"key":16,"text":17,"correct":18},"B","回收固定资产余值",false,{"key":20,"text":21,"correct":18},"C","回收流动资金",{"key":23,"text":24,"correct":14},"D","借款利息支付",{"key":26,"text":27,"correct":14},"E","经营成本","ADE","2013年建设工程经济真题第64题 本题考查的是资本金现金流量表的编制。 资本金现金流量表是从技术方案权益投资者整体（即项目法人）角度出发，以技术方案资本金作为计算的基础，把借款本金偿还和利息支付作为现金流出。 因此，ADE项正确。选项BC属于现金流入。*",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]