[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137661":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137661,798,2,"多选题","建设项目敏感性分析中，确定敏感因素可以通过计算（ ）来判断。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","盈亏平衡点",false,{"key":16,"text":17,"correct":14},"B","评价指标变动率",{"key":19,"text":20,"correct":14},"C","不确定因素变动率",{"key":22,"text":23,"correct":24},"D","临界点",true,{"key":26,"text":27,"correct":24},"E","敏感度系数","DE","2010年建设工程经济真题第62题 本题主要考查了单因素敏感性分析的步骤。 敏感性分析的目的在于寻求敏感因素，可以通过计算敏感度系数和临界点来判断。 综上所述，本题正确答案为DE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]