[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137618":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137618,798,2,"多选题","建设项目财务评价时，可以采用静态评价指标进行评价的情形有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目年收益大致相等",true,{"key":16,"text":17,"correct":14},"B","项目寿命期较短",{"key":19,"text":20,"correct":21},"C","评价精度要求较高",false,{"key":23,"text":24,"correct":14},"D","可以不考虑资金的时间价值",{"key":26,"text":27,"correct":21},"E","项目现金流量变动大","ABD","2009年建设工程经济真题第80题 本题主要考查了经济效果评价指标体系。 静态分析指标的最大特点是不考虑时间因素，计算简便。所以在对技术方案进行粗略评价，或对短期投资方案进行评价，或对逐年收益大致相等的技术方案进行评价时，静态分析指标还是可采用的。 综上所述，本题正确答案为ABD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]