[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137595":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137595,798,2,"多选题","投资者自行测定技术方案的最低可接受财务收益率时，应考虑的因素有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","沉没成本",false,{"key":16,"text":17,"correct":18},"B","自身的发展战略和经营策略",true,{"key":20,"text":21,"correct":18},"C","资金成本",{"key":23,"text":24,"correct":18},"D","技术方案的特点和风险",{"key":26,"text":27,"correct":18},"E","机会成本","BCDE","2011年建设工程经济真题第65题 本题主要考查了基准收益率的测定。 BCDE项：投资者自行测定技术方案的最低可接受财务收益率，应根据自身的发展战略和经营策略、技术方案的特点与风险、资金成本、机会成本等因素综合测定。因此，BCDE项正确。 A项：沉没成本是既有企业过去投资决策发生的，非现在决策能改变（或不受现在决策影响）、已经计入过去投资费用回收计划的费用。因此，A项错误。 综上所述，本题正确答案为BCDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]