[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1137562,798,1,"单选题","某建设项目估计总投资2800万元，项目建成后各年净收益为320万元，利率为10%。则该项目的静态投资回收期为（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":18},"B","8.75",true,{"key":20,"text":21,"correct":14},"C","9.95",{"key":23,"text":24,"correct":14},"D","7.5","2005年建设工程经济真题第5题 本题考查的是静态投资回收期的计算。 当技术方案实施后各年的净收益（即净现金流量）均相同时，静态投资回收期的计算公式如下： 式中：I为项目投入的全部资金；A为每年的净现金流量，即 。 因为静态分析指标不考虑时间因素，故利率的信息在本题中为干扰因素。 本题静态投资回收期=2800\u002F320=8.75（年）。 综上所述，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]