[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1137556,798,1,"单选题","某项目建设投资为1000万元，流动资金为200万元，建设当年即投产并达到设计生产能力，年净收益为340万元，则该项目的静态投资回收期为（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7.14",false,{"key":16,"text":17,"correct":18},"B","3.53",true,{"key":20,"text":21,"correct":14},"C","2.94",{"key":23,"text":24,"correct":14},"D","2.35","2009年建设工程经济真题第19题 本题主要考查了静态投资回收期的计算。 静态投资回收期可根据净现金流量计算，其具体计算又可根据技术方案实施后各年的净收益是否相同分为两种情况。本题技术方案实施后各年的净收益相同的情况。 因此，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]