[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1137543,798,1,"单选题","某项目的财务净现值前5年为210万元，第6年末30万元，=10%，则前6年的财务净现值为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","227",true,{"key":16,"text":17,"correct":18},"B","237",false,{"key":20,"text":21,"correct":18},"C","240",{"key":23,"text":24,"correct":18},"D","261","2006年建设工程经济真题第5题 此题考查财务净现值的概念及计算。 财务净现值是反应技术方案在计算期内盈利能力的动态评价指标。其计算公式为： 本题中，第六年的财务净现值为 所以前六年财务净现值=17+210=227（万元）。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]