[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137490":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137490,798,2,"多选题","技术方案经济效果评价的程序包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","熟悉技术方案的基本情况",true,{"key":16,"text":17,"correct":18},"B","了解国家经济政策和产业政策",false,{"key":20,"text":21,"correct":14},"C","收集、整理和计算有关技术经济基础数据资料与参数",{"key":23,"text":24,"correct":14},"D","根据基础财务数据资料编制各基本财务报表",{"key":26,"text":27,"correct":14},"E","经济效果评价","ACDE","本题的考点是经济效果评价的程序。 经济效果评价的程序为： （1）熟悉技术方案的基本情况； （2）收集、整理和计算有关技术经济基础数据资料与参数； （3）根据基础财务数据资料编制各基本财务报表； （4）经济效果评价。 综上所述，本题的正确答案为ACDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]