[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137420":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1137420,798,1,"单选题","某项目投资来源中，项目资本金2000万元，借入银行资金1000万元，建设期借款利息200万元。在编制项目财务现金流量表时，建设期现金流入的投资应为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1200",false,{"key":16,"text":17,"correct":14},"B","2000",{"key":19,"text":20,"correct":21},"C","3000",true,{"key":23,"text":24,"correct":14},"D","3200","2006年建设工程经济真题第1题 此题考查的是现金流量的概念。 技术方案整个期间各时点t上实际发生的资金流出或资金流入称为现金流量，故利息不计入现金流量。本题中，项目资本金2000万元与借入银行资金1000万元之和，共3000万元，即建设期现金流入的投资。 综上所述C项正确。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]