[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1137412,798,1,"单选题","（2019年真题）某施工单位拟投资一项目，在投资总额和年收益不变的情况下，四个备选方案各年投资比例如下表（投资时点均相同），则对该单位较为有利的方案是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","方案一",false,{"key":16,"text":17,"correct":14},"B","方案二",{"key":19,"text":20,"correct":14},"C","方案三",{"key":22,"text":23,"correct":24},"D","方案四",true,"P1-5 在总资金一定的情况下，前期投入的资金越多，资金的负效益越大；反之，后期投入的资金越多，资金的负效益越小。而在资金回收额一定的情况下，离现在越近的时间回收的资金越多，资金的时间价值就越多;反之，离现在越远的时间回收的资金越多，资金的时间价值就越少。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]