[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137385":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137385,797,2,"多选题","（2011年真题）工程开工前，项目部编制“计量检测设备配备计划书”的依据是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工组织设计",true,{"key":16,"text":17,"correct":18},"B","计量检测设备使用说明书",false,{"key":20,"text":21,"correct":18},"C","作业指导书",{"key":23,"text":24,"correct":14},"D","质量计划",{"key":26,"text":27,"correct":14},"E","施工方案","ADE","本题考查的是计量鉴定的要求。工程开工前，项目部应根据项目质量计划、施工组织设计、施工 方案对检测设备的精度要求和生产需要，编制“计量检测设备配备计划书”。依据计量检定规程，按规定 的检定周期，结合实际使用情况、合理安排送检计量器具，确保计量检测设备使用前已按规定要求检定合 格",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]