[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137382":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137382,797,2,"多选题","（2014年真题）建筑安装工程检验批主控项目有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对卫生、环境保护有较大影响的检验项目",false,{"key":16,"text":17,"correct":18},"B","确定该检验批主要性能的项目",true,{"key":20,"text":21,"correct":14},"C","无法定量采用定性的项目",{"key":23,"text":24,"correct":18},"D","管道的压力试验",{"key":26,"text":27,"correct":18},"E","保证安全和使用功能的重要检验项目","BDE","本题考查的是建筑安装工程检验批、分项工程质量验收评定合格的标准。主控项目的要求是必须 达到的，是保证安装工程安全和使用功能的重要检验项目，是对安全、卫生、环境保护和对公众利益起决 定性作用的检验项目，是确定该检验批主要性能的项目。如果达不到主控项目规定的质量指标，降低要求 就相当于降低该工程项目的性能指标，导致严重影响工程的安全和使用性能。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]