[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137379":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137379,797,2,"多选题","（2012年真题）工业安装工程分项工程质量验收记录填写的主要内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","检验项目",true,{"key":16,"text":17,"correct":14},"B","施工单位检验结果",{"key":19,"text":20,"correct":21},"C","设计单位验收结论",false,{"key":23,"text":24,"correct":14},"D","监理单位验收结论",{"key":26,"text":27,"correct":14},"E","建设单位验收结论","ABDE","本题考查的是分项工程质量验收。分项工程质量验收记录应由施工单位质量检验员填写，验收结 论由建设（监理）单位填写。填写的主要内容：检验项目；施工单位检验结果：建设（监理）单位验收结 论。结论为“合格”或“不合格”。记录表签字人为施工单位专业技术质量负责人、建设单位专业技术负 责人、监理工程师。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]