[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137375":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137375,797,2,"多选题","（2017年真题）关于材料进场验收要求的说法，正确的有（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","要求进场复验的材料应有取样送检证明报告",true,{"key":16,"text":17,"correct":14},"B","验收工作应按质量验收规范和计量检测规定进行",{"key":19,"text":20,"correct":14},"C","验收内容应完整，验收要做好记录，办理验收手续",{"key":22,"text":23,"correct":24},"D","甲供的材料只做好标记",false,{"key":26,"text":27,"correct":24},"E","对不符合计划要求的材料可暂缓接受","ABC","材料进场验收要求 1）进场验收、复检。在材料进场时必须根据进料计划、送料凭证、质量保证书或产品合格证，进行材料 的数量和质量验收；要求复检的材料应有取样送检证明报告，A 对； 2）按验收标准、规定验收。验收工作按质量验收规范和计量检测规定进行，B 对； 3）验收内容应完整。包括品种、规格、型号、质量、数量、证件等，C 对； 4）做好记录、办理验收。验收要做好记录、办理验收手续，D 错； 5）不符合、不合格拒绝接收。对不符合计划要求或质量不合格的材料应拒绝接收，E 错。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]