[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137372":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137372,797,2,"多选题","（2018年真题）设备采购监造时，停工待检点应包括（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","重要工序节点",true,{"key":16,"text":17,"correct":14},"B","隐蔽工程",{"key":19,"text":20,"correct":21},"C","设备性能重要的相关检验",false,{"key":23,"text":24,"correct":14},"D","不可重复试验的验收点",{"key":26,"text":27,"correct":14},"E","关键试验的验收点","ABDE","停工待检（H）点设置 （1）重要工序节点、隐蔽工程、关键的试验验收点或不可重复试验验收点。 （2）停工待检（H）点的检查重点之一是验证作业人员上岗条件要求的质量与符合性。例如：压力容器的水压试验就属于停工待检点。监督人员须按标准规定监视作业，确认该点的工序作业。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]